Photos Of The Ongoing Construction Of 11.9KM Second Niger Bridge

Second Niger Bridge is over 40% complete.

Significant work has been done along the 11.9km stretch of on-going construction.

The decking phase for the bridge commences next week and will last for another 32 weeks!

Julius Berger to finish the 11.9km stretch of the Second NigerBridge in 2 years.

When the 1st Niger Bridge and Third Mainland Bridge were constructed, our nation imported 90% of the cement to create jobs abroad, but today the billions spent buying cement get millions employed here.

97 Views

501xclusive

Leave a Reply

Your email address will not be published. Required fields are marked *

Next Post

7 Chairmen, 42 Councilors, Others Dump PDP For APC In Ekiti

Sat Nov 30 , 2019
No fewer than 500 card-carrying members of People Democratic Party in Ekiti State including seven serving local government chairmen and 42 Councilors elected on the party’s platform have defected to the All Progressives Congress (APC). The defectors with their supporters were on Friday received by Governor Kayode Fayemi into the […]